From National Highways
Work is planned to start on Monday 1st September 2025, and we expect to complete early 2026.
To complete our work safely, we’ll work overnight using a combination of full closures and lane closures to reduce disruption. Our work at this location will also include a series of weekend closures. Further updates will be provided at the earliest opportunity.
Traffic Management
- From 1 September to 5 September, A14 closed westbound, 9pm to 5am.
- From 8 September to 12 September, A14 closed eastbound, 9pm to 5am.
- From 22 September to 26 September, A14 closed westbound, 9pm to 5am.
- From 29 September to approximately mid-November, A14 closed eastbound, Monday to Friday, 9pm to 5am.
- From approximately mid-November to early 2026, A14 closed westbound, Monday to Friday, 9pm to 5am. No closures will be in place over the Christmas holidays.
We do require two full weekend closures that are currently planned for eastbound in October and westbound in January 2026, exact dates will be confirmed in due course. Throughout this time, we’ll close the road from 8pm on Friday to 6am on Monday morning. These are required for the installations of the new expansion
Traffic will be diverted along the A6/A45 between A14 junctions 10 and 13 when closures are in affect.
Access for emergency service vehicles will be maintained throughout.
We’ll make every effort to ensure the impact on the local community and travelling public is kept to a minimum. We always aim to work to the programme, however unforeseen circumstances or adverse weather conditions may mean changes.
Please accept our apologies in advance for any inconvenience this may cause.